Findings — 4 highlighted provisions

Each item below is one provision documented in the findings file. The same provision is highlighted in the full text underneath, with its section citation and criterion. Everything else on this page is plain, unreviewed bill text.

  1. Sec. 2(a)(1)(B) · Economic Freedom — It lets the Nuclear Regulatory Commission issue a permit or license without a hearing, on 30 days' notice, when no hearing has been requested, removing a procedural delay in nuclear licensing See in text ↓
  2. Sec. 2(c) · Economic Freedom — It limits the hearing requirement for uranium enrichment facilities to cases in which an affected person requests a hearing, streamlining those licensing proceedings See in text ↓
  3. Sec. 2(a)(1)(B) · Privacy and Due Process — It allows a permit or license to issue without a hearing unless one is requested and provides for informal adjudicatory procedures when a hearing is held, reducing the hearing rights available in licensing proceedings See in text ↓
  4. Sec. 2(c)(1) · Privacy and Due Process — It strikes the requirement that hearings on uranium enrichment facility licenses be held on the record under section 554 of title 5, so such hearings are held only if an affected person requests one See in text ↓

Full text (introduced version)

5 of 14 text blocks highlighted. Source: GovInfo, fetched cached.

[Congressional Bills 119th Congress] [From the U.S. Government Publishing Office] [H.R. 5549 Introduced in House (IH)] <DOC> 119th CONGRESS 1st Session H. R. 5549 To amend the Atomic Energy Act of 1954 to provide for more efficient hearings on nuclear facility construction applications, and for other purposes. _______________________________________________________________________ IN THE HOUSE OF REPRESENTATIVES September 23, 2025 Mr. Griffith (for himself, Ms. Schrier, and Mr. Veasey) introduced the following bill; which was referred to the Committee on Energy and Commerce _______________________________________________________________________ A BILL To amend the Atomic Energy Act of 1954 to provide for more efficient hearings on nuclear facility construction applications, and for other purposes. Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled,

SECTION 1. SHORT TITLE.

This Act may be cited as the ``Efficient Nuclear Licensing Hearings Act''.

SEC. 2. UPDATING HEARING PROCEDURES.

Sec. 2(a)(1)(B) · Economic Freedom — It lets the Nuclear Regulatory Commission issue a permit or license without a hearing, on 30 days' notice, when no hearing has been requested, removing a procedural delay in nuclear licensing

Sec. 2(a)(1)(B) · Privacy and Due Process — It allows a permit or license to issue without a hearing unless one is requested and provides for informal adjudicatory procedures when a hearing is held, reducing the hearing rights available in licensing proceedings

(a) Hearings and Judicial Review.--Section 189 a. of the Atomic Energy Act of 1954 (42 U.S.C. 2239(a)) is amended--

Sec. 2(a)(1)(B) · Economic Freedom — It lets the Nuclear Regulatory Commission issue a permit or license without a hearing, on 30 days' notice, when no hearing has been requested, removing a procedural delay in nuclear licensing

Sec. 2(a)(1)(B) · Privacy and Due Process — It allows a permit or license to issue without a hearing unless one is requested and provides for informal adjudicatory procedures when a hearing is held, reducing the hearing rights available in licensing proceedings

(1) in paragraph (1)(A)-- (A) by striking ``In any proceeding under this Act'' and inserting the following:
``(i) In any proceeding under this Act''; and
(B) in clause (i) (as so designated), by striking ``The Commission shall hold a hearing'' and all that follows through ``upon a determination by the Commission that the amendment involves no significant hazards consideration.'' and inserting the following:
``(ii) The Commission may, in the absence of a request for a hearing by any person whose interest may be affected, issue a construction permit, an operating license, a combined construction permit and operating license, an amendment to a construction permit, an amendment to an operating license, or an amendment to a combined construction permit and operating license under section 103, 104 b., 104 c., or 185 b. for a facility or a testing facility, without a hearing, but upon thirty days notice and publication once in the Federal Register of its intent to do so. The Commission may dispense with such thirty days notice and publication with respect to any application for an amendment to a construction permit, an amendment to an operating license, or an amendment to a combined construction permit and operating license upon a determination by the Commission that the amendment involves no significant hazards consideration.
``(iii) The Commission shall use informal adjudicatory procedures for any hearing held by the Commission pursuant to this subparagraph.'';
(2) in paragraph (1)(B)(iv)-- (A) by inserting ``informal'' before ``hearing procedures''; and (B) by striking ``, whether informal or formal adjudicatory,''; and
(3) in the second sentence of paragraph (2)(A), by striking ``required hearing'' and inserting ``hearing held by the Commission under this section''.
(b) Construction Permits and Operating Licenses.--Section 185 b. of the Atomic Energy Act of 1954 (42 U.S.C. 2235(b)) is amended by striking ``After holding a public hearing under section 189 a. (1)(A),'' and inserting ``After the thirty days notice and publication period or holding a hearing, as applicable, under section 189 a. (1)(A),''.

Sec. 2(c) · Economic Freedom — It limits the hearing requirement for uranium enrichment facilities to cases in which an affected person requests a hearing, streamlining those licensing proceedings

Sec. 2(c)(1) · Privacy and Due Process — It strikes the requirement that hearings on uranium enrichment facility licenses be held on the record under section 554 of title 5, so such hearings are held only if an affected person requests one

(c) Licensing of Uranium Enrichment Facilities.--Section 193(b) of the Atomic Energy Act of 1954 (42 U.S.C. 2243(b)) is amended by--

Sec. 2(c) · Economic Freedom — It limits the hearing requirement for uranium enrichment facilities to cases in which an affected person requests a hearing, streamlining those licensing proceedings

Sec. 2(c)(1) · Privacy and Due Process — It strikes the requirement that hearings on uranium enrichment facility licenses be held on the record under section 554 of title 5, so such hearings are held only if an affected person requests one

(1) in paragraph (1)-- (A) by striking ``on the record''; and (B) by inserting ``if a person whose interest may be affected by such construction and operation has requested a hearing regarding the licensing of the construction and operation of the facility'' after ``and 63''; and

Sec. 2(c) · Economic Freedom — It limits the hearing requirement for uranium enrichment facilities to cases in which an affected person requests a hearing, streamlining those licensing proceedings

(2) in paragraph (2), by striking ``Such hearing'' and inserting ``If a hearing is held under paragraph (1), the hearing''.
(d) Applicability.--The amendments made by this section shall apply to all applications and proceedings pending before the Nuclear Regulatory Commission on or after the date of enactment of this section. <all>

Findings source: bill-scores-v2-batch6-findings-2026-11-16.md. Highlights come only from that file; no finding, score, or provision was invented for this page.

What you can do

Contact your U.S. Representative and Senators about this bill.

Find your Representative Contact your Senators

Spot an error on this page? Report it.